Ep. 018 - Stop Saying Half of 2026 US Datacenter Capacity Is Canceled (Datacenter, Energy) | Jeremie Eliahou Ontiveros, Reyk Knuhtsen, Ellie Holbrook, Jordan Nanos
Notas do episódio
Bloomberg said half of 2026 US data center capacity is delayed. The SemiAnalysis Data Center, Energy, and Industrials team pulled the underlying report and found a broken denominator. Amazon alone built 4GW in 2025 and is adding 5GW plus in 2026. CoreWeave adds a gigawatt, all under construction. Jeremie Eliahou Ontiveros (@JeremieEO), Reyk Knuhtsen (@robotknower), and Ellie Holbrook join Jordan Nanos (@JordanNanos) as they walk through why the number is wrong and what the real forecast shows. …